Bury Cabinet is asked on 2 December to back compulsory purchase, if talks fail, for land on Pilsworth Road. GMCA has lined up £62.1m for the scheme.

Bury Council’s Cabinet is being asked to agree in principle to compulsory purchase of land for the Pilsworth Road and M66 junction 3 scheme. The powers would be used only if the council cannot buy the land by agreement in time.

The request is in a report to Cabinet for its meeting on Wednesday 2 December. The scheme is called the Northern Gateway Western Access. A public consultation on its design is running until December.

What Cabinet is asked to agree

The report asks Cabinet to:

  • let officers investigate using compulsory purchase powers for the land the scheme needs
  • agree in principle to use those powers if negotiation does not work within a reasonable time
  • let the Executive Director of Place start surveys, valuations and talks with owners, and buy land by agreement

A compulsory purchase order would not be made yet. The report says a second Cabinet report would be needed for that, once the boundary and the list of owners are fixed. It expects that work to be done by early spring 2027.

What land is involved

The report describes the land as “strips of verges, woodland screening and other minor land parcels” next to the existing road. It says these have “limited commercial value”. Some land would also be needed for a while for contractor compounds and work areas. For those, the council would aim to lease the land rather than buy it.

The report says offers to owners should reflect any effect on their business, such as disruption or access during the works, not only the value of the land.

The cost

The estimated land and compulsory purchase budget is £1,259,196. The report breaks it down as:

Item Estimate
Land and property £632,664
Temporary works and site compound £126,532
A compulsory purchase public inquiry £500,000

The report says this fits within the scheme’s overall budget.

The road scheme itself is funded by the Greater Manchester Combined Authority. The report gives £10m of Investment Zone grant, plus £52.1m of Good Growth money “indicatively allocated”. The consultation page published on 18 November gave no cost for the scheme.

Why the council says it needs the powers now

The money comes with deadlines. The report lists them:

  • preliminary designs finished by early 2027
  • an outline business case submitted in February 2027
  • detailed designs, costings and a full business case by summer 2028
  • construction starting by autumn 2028

It warns that missing these milestones would put the grant at risk. It says compulsory purchase “should never be seen as a first option”, but government guidance allows it to run alongside negotiation because it takes time.

What the scheme would change

The report lists the main works:

  • an upgrade of the Asda roundabout at Pilsworth Retail Park
  • extra lanes on the M66 junction 3 slip roads
  • an upgraded signal junction at Pilsworth Road and Moss Hall Road, by Great Bear
  • a shared walking and cycling route along the corridor, including under the junction 3 bridge
  • lower speed limits west of the M66 junction

The road is meant to open up the first phases of the Northern Gateway employment site, on the border with Rochdale.

What it means for you

  • If you own or rent land along Pilsworth Road, the report says the council will negotiate with owners and that “acquisition by agreement should take priority”.
  • The design consultation is still open. Our report on it has the drop-in details and how to respond.
  • The Cabinet meeting is at 6pm on Wednesday 2 December. The papers are on the council’s meetings page.