Up to 119 vehicles a day will serve the Haweswater aqueduct works at Woodgate Hill in Bury, using Castle Hill Road. Shaft digging is planned from April 2027.
Up to 119 lorries and vans a day are expected to use Castle Hill Road and Rochdale Old Road this winter, as work builds up on a new section of the Haweswater Aqueduct at Woodgate Hill. The traffic will continue in smaller numbers until late 2031.
Updated 14 November: United Utilities is holding a drop-in for Woodgate Hill residents on Thursday 19 November, 2pm to 7pm, at St John the Baptist Church on Castle Hill Road. Details below.
The figures are in a construction traffic plan sent to Bury Council on 10 November by STRABAG, the contractor building the scheme for United Utilities. The plan (application 73853) covers the deepest and longest parts of the job: sinking a shaft at the Woodgate Hill water treatment works and receiving the tunnel boring machine that will dig its way there from Haslingden.
What is being built
The 110km Haweswater Aqueduct was built between 1933 and 1955. It carries 570 million litres of drinking water a day to 2.5 million customers in Cumbria, Lancashire and Greater Manchester, according to United Utilities’ exhibition boards from its July drop-in at Castle Hill.
The Haweswater Aqueduct Resilience Programme will replace six tunnel sections, about 50km in all, at a cost of nearly £3 billion. The company says the new aqueduct will be working by 2033.
The southern end of the aqueduct is the treatment works at Woodgate Hill, east of the M66 and about 2km from Bury town centre. From a compound at Haslingden, a new tunnel will be bored south to it. Bury Council granted planning permission (66947) for the Bury works in June 2023.
The timetable
The plan gives these dates for the Woodgate Hill compound:
| Stage | What happens | Planned dates |
|---|---|---|
| Phase 1 | Site set-up, haul roads, topsoil removal, entrance junction | 28 August 2026 to 28 February 2027 |
| Phase 2 | Excavation, ground stabilisation, foundations, cranes | 10 December 2026 to 1 March 2027 |
| Phase 3a | Digging the shaft, below-ground structures | 20 April 2027 to 26 March 2030 |
| Phase 4 | Tunnel boring machine arrives and is taken apart, pipe connections, buildings | 18 August 2027 to 13 November 2031 |
The council approved the traffic arrangements for phases 1 and 2 on 7 August, according to STRABAG’s covering letter. The new application is for phases 3a and 4. United Utilities’ boards in July said shaft construction would begin in March 2027. The contractor’s plan now gives 20 April.
How many vehicles, and when
The plan forecasts these daily averages, measured over a week:
- Now to spring 2027: up to 119 vehicles a day, of which 70 are heavy goods vehicles and 49 are vans
- Shaft and tunnel stages, 2027 to 2031: up to 84 vehicles a day, of which 50 are heavy goods vehicles and 34 are vans
Workers’ own cars are not included in those figures. The lorries will mostly bring plant, cabins and stone, and take away excavated earth.
Working hours and lorry deliveries are limited to:
- Monday to Friday, 7am to 7pm
- Saturday, 7am to 1pm
- no work or deliveries on Sundays or bank holidays
Abnormal loads may move outside those hours if the council, Transport for Greater Manchester and National Highways agree in advance. Vans have no time restriction.
The route lorries must use
Site traffic is only allowed on one route, set by a planning condition:
- leave the M66 at junction 2 and head west on Rochdale Road
- turn onto Derby Way, then the B6222 along Moorgate, Bell Lane and Rochdale Old Road
- turn onto Castle Hill Road
For the first few months, lorries reach the site through the existing United Utilities entrance via Second Avenue and Sixth Avenue. The plan says this is for 12 to 16 weeks. A separate application (73659) asks to keep using it for up to about 36 weeks.
A new main entrance is being built off Castle Hill Road, between Woodgate Hill Memorial Forest and Kelwood Avenue. It is due to open in January 2027, with a longer footway and a crossing point.
Parking changes
The plan says the council has agreed to:
- suspend parking on the west side of Castle Hill Road on weekdays from 8am to 5pm and on Saturdays from 8am to 1pm, with double yellow lines enforced from January 2027
- suspend parking on Second Avenue for three months, through a traffic order with eight weeks’ notice
The compound will have 80 parking spaces for its own workforce from February 2027. During the first two phases it has 10.
United Utilities told residents in July that all roads would stay open, with no road closures.
Drop-in on 19 November
United Utilities is inviting residents of the Woodgate Hill area to a drop-in session about the works. It runs from 2pm to 7pm on Thursday 19 November at St John the Baptist Church on Castle Hill Road. The company announced it on 12 November in a press release.
Staff from United Utilities and Cascade Infrastructure, the delivery partner, will be there. The release says work on the new compound at the Woodgate Hill treatment works is already under way. It is being carried out by STRABAG on behalf of Cascade Infrastructure.
It follows an earlier drop-in at the same church in the summer. The session is a chance to ask about the lorry numbers, parking suspensions and new entrance set out above.
What it means for you
If you live on or near Castle Hill Road, Second Avenue or Sixth Avenue, expect parking restrictions and a steady flow of lorries on weekdays and Saturday mornings. Signs warning drivers about Fairfield Community Primary School are part of the plan.
Bus routes on Rochdale Road and Rochdale Old Road share the lorry route. The plan names the 94, 163, 471, 475, 467, 468, 472 and 474. It says no specific changes are needed, and that STRABAG will talk to the bus operators before the main works begin.
Every lorry leaving the site has to pass through a wheel wash, to keep mud off the road. The plan asks hauliers to fit GPS trackers so that the permitted route can be enforced.
Bury Council has not yet decided the new application. The documents are on the council’s planning register under reference 73853.
Have your say