Willmott Dixon starts the £17.9m first phase in mid-November: a 57-metre footbridge and new tram platforms. Part of the Metrolink car park becomes a compound.
Updated 17 November: TfGM has confirmed the Metrolink car park will be closed completely from Monday 23 to Friday 27 November while the compound is set up, with 100 free spaces at Q-Park Knowsley Place.
Building work on Bury Interchange starts in mid-November. It is the first construction on the site since Transport for Greater Manchester (TfGM) set out plans to rebuild it.
The contract for phase one has gone to Willmott Dixon. The builder announced the £17.9m job on 2 November and says it will finish in early 2028.
This phase is the tram side only. The bus station stays open and buses keep running as normal for now.
The change most people will notice first is parking. From mid-November, part of the Metrolink car park on Angouleme Way becomes a site compound, TfGM says. There will be fewer spaces at the interchange.
What gets built in phase one
TfGM’s project page lists the work:
- a new footbridge over the Metrolink lines, linking to Union Square, with step-free access to Pyramid Park along a new path
- new stairs and a lift down from the footbridge to the tram platforms
- new canopies and resurfaced platforms
- better ticketing, new passenger information displays and new driver facilities
- upgraded lighting, signage and CCTV
- a temporary stepped entrance at the north end of the eastern platform, giving a more direct route into town
Willmott Dixon says the footbridge is a 57-metre steel structure. TfGM says it will be permanent. Its job is to keep the tram platforms reachable once the interchange building itself closes for phase two.
The temporary stepped entrance is due to open to the public in late 2027 or early 2028, before the main interchange work begins.
Bury Council approved the phase one plans, application 71834, with conditions on 24 July 2025. That approval also covers filling in the existing underpass, according to the council’s planning register. We covered the full approved description in September.
Who is building it, and what it cost
Willmott Dixon was appointed through the SCAPE Construction Framework, a public sector procurement route. It is the same firm that built TfGM’s £140m Stockport Interchange, the scheme TfGM has said it wants Bury to follow.
The money comes from the government’s City Region Sustainable Transport Settlement. Greater Manchester was awarded £1.07bn under it, and TfGM lists Bury Interchange as a named project within that programme.
Vernon Everitt, Greater Manchester’s Transport Commissioner, said in Willmott Dixon’s announcement: “Starting next month, we will begin to turn this outdated facility into a modern, accessible and welcoming place, putting public transport at the heart of the town’s regeneration.”
Anthony Dillon, Willmott Dixon’s managing director in the North, said the work would provide “a 57-meter steel pedestrian footbridge and essential platform and access upgrades to support Phase 2 of the Interchange’s redevelopment”.
Where to park instead
TfGM lists 96 spaces at the Bury Metrolink park and ride, plus 4 disabled bays. It has not said how many will go to the compound.
The car park closes completely from Monday 23 to Friday 27 November, TfGM says. Accessible bays stay open, and 100 free spaces are available at Q-Park Knowsley Place, first come, first served. It reopens on Saturday 28 November with fewer spaces.
It points drivers to two other Metrolink car parks on the same line. Both are free with a valid Metrolink ticket.
| Car park | Address | Spaces | Disabled bays |
|---|---|---|---|
| Bury | Angouleme Way, BL9 0AY | 96 | 4 |
| Whitefield | Stanley Road, M45 8QH | 318 | 13 |
| Radcliffe | Spring Lane, M26 2SZ | 458 | 22 |
Radcliffe and Whitefield both have a 2.3m height limit, according to TfGM.
What it means for you
- If you drive to the tram at Bury, expect fewer spaces from mid-November. Radcliffe and Whitefield are the official alternatives. Town centre car parks are on our parking in Bury page.
- If you catch a bus, nothing changes yet. TfGM expects the bus station to close for rebuilding in early 2028, and says buses will run to and from the town centre every day throughout.
- If you take the tram, trams keep running into the interchange for most of the work. TfGM says there will be times they cannot, and that it will announce those in advance with replacement buses. We list current closures on our Bury roadworks and travel page.
- If you want a say on the new bus station, phase two goes to a formal public consultation that TfGM now says is scheduled to launch in winter 2026.
The footbridge lands next to the council land at Pyramid Park, where 215 homes are proposed. Other applications in the borough are on our Bury planning news page.
Sources
- Bury Interchange project page, Transport for Greater Manchester, read 3 November 2026
- Willmott Dixon to deliver £17.9m Phase 1 redevelopment of Bury Interchange, Willmott Dixon, 2 November 2026
- Two weeks to go until work starts on major redevelopment of Bury Interchange, TfGM newsroom (headline and photograph)
- Park and ride pages for Bury, Whitefield and Radcliffe, TfGM, read 3 November 2026
- Planning application 71834, Bury Council