Cabinet is asked on 4 November to tender seven road, crossing and bridge schemes worth about £15m, from Palatine Street in Ramsbottom to the Radcliffe tram ramp.
Seven road, crossing and bridge schemes across Bury borough, worth about £15 million between them, are set to go out to tender. Bury Council’s Cabinet is asked to approve the step on Wednesday 4 November.
Updated 5 November: the council’s record now lists the tender approval as “Recommendations Approved (subject to call-in)” after the 4 November Cabinet.
The money is all external. It comes from the Greater Manchester City Region Sustainable Transport Settlement and the Active Travel Fund, both government transport funding. The report to Cabinet says there is no cost to the council.
The seven schemes are:
- Bury town centre Streets for All, phase 1, including Baron Street
- Radcliffe town centre Streets for All, phase 1, including Spring Lane
- Ramsbottom town centre Streets for All, phase 1
- a ramp to Radcliffe Metrolink stop
- traffic lights at three Parkhills mini-roundabouts in Bury
- a new Elton Bridge over the Irwell, with work on Hinds Lane
- a fix for the bus bottleneck at Hollins Brow
Tendering now gets real prices. The council needs them to finish each scheme’s full business case for Transport for Greater Manchester (TfGM). The report warns that delay would put the funding at risk.
Ramsbottom: Palatine Street to close
The Ramsbottom plans have changed a lot since 2024. The council’s Streets for All Ramsbottom page says the 2024 consultation drew 1,504 responses. The one-way system people objected to has been dropped.
What is still proposed:
- a 20mph limit across the town centre streets, including Kay Brow
- Palatine Street closed to traffic, so the cycle route to Nuttall Park can come off Railway Road
- new signal-controlled crossings at Bridge Street and Palatine Street, and at Railway Street and Union Street
- new controlled crossings on Bolton Street, north of Kay Brow and just north of Callendar Street and Cross Street
- raised table crossings on Bridge Street, Bolton Street, Railway Street, Square Street, Silver Street, Factory Street, Crow Lane and Kay Brow
- Union Street rerouted round the car park, with access limited to residents, businesses and deliveries, and the end at Railway Street open only to people on foot and bikes
- a widened shared path on Bridge Street between Crow Lane and the new crossing
- wider paths through Nuttall Park, and the barriers at the Nuttall Hall Road bridge taken out
The drawings attached to the Cabinet report also mark parking that would go: one note reads “10 ‘one hour no return’ parking bays removed”, and another marks five more bays (20m) of the same kind.
The council’s page says that if councillors approve the scheme, building is expected to start in 2027 and take about 12 months.
Radcliffe: Spring Lane and the tram stop ramp
The Radcliffe scheme improves walking and cycling on Spring Lane, between the town centre and the new STAR academy school, the report says. The council’s Radcliffe Streets for All page lists the wider plan:
- walking, wheeling and cycling improvements on Spring Lane and Blackburn Street
- “Quiet Streets” on Whittaker Street, Darbyshire Street and Green Street
- better links to the canal towpath on Water Street
- improvements on Church Street West and Deansgate
It says the work must be finished by 2027.
The Metrolink ramp is a separate scheme. It would give a lit, shared ramp up to the eastern platform of Radcliffe tram stop. It would meet a new toucan crossing on Church Street West, and a “modal filter”, a point that stops through traffic but lets people on foot and bikes pass, on the line out of Glebe Street. The report says that links to new routes from the planned homes on the old East Lancashire Paper Mill site. The ramp already has planning permission, reference 71284.
Bury: Parkhills, Baron Street and Elton Bridge
Parkhills. Three existing mini-roundabouts would become four-arm junctions with traffic lights and pedestrian crossings. The scheme also includes new kerbs, drainage and “an extensive resurfacing package”, the report says. The drawings centre on Parkhills Road.
Baron Street. The report describes it as “an existing heavily used pedestrian route between the town centre and local schools”. The town centre scheme would give it proper walking, wheeling and cycling space. Consultation on the wider Bury town centre links plans ran from 29 June to 10 August 2026, and the council has not yet published the results.
Elton Bridge. The current footbridge over the River Irwell off Hinds Lane is a 1m wide precast concrete crossing. The plan is a 3.5m wide steel bridge for people on foot and on bikes. The path to the canal towpath would be widened, sealed, drained and lit. Unlike the others, this scheme is down to “future funding programmes”, so the money is not yet in place.
Hollins: the bus bottleneck
Hollins Brow meets the A56 Manchester Road at a junction the report calls “an existing bottleneck” for buses. The plan is new signal positions and kerb lines so the lights spend less time with all traffic stopped.
What happens next
If Cabinet agrees, the schemes are tendered through the TC005 Highways Construction Framework. The decision to award each contract would be delegated to senior officers and the cabinet member for environment, climate change and operations. That happens only once TfGM or the funder has approved each full business case.
If prices come in higher than expected, the report says each scheme’s value for money will be looked at again. The report gives no cost for any single scheme and no start dates except for Ramsbottom.
What it means for you
- If you drive in Ramsbottom, Palatine Street would close to traffic and the town centre would go to 20mph, but there will be no one-way system. Work would not start before 2027.
- If you walk to school in Bury or Radcliffe, Baron Street and Spring Lane are the routes the money is aimed at.
- If you use Radcliffe tram stop with a pram, bike or wheelchair, a ramp to the eastern platform is in the package.
- If you want to follow it, Cabinet meets on Wednesday 4 November. The agenda and drawings are on the council’s site.
Roadworks already under way across the borough, including the Bury Old Road resurfacing from 2 November, are on our Bury roadworks page.
Sources
- Bury Council, Approval to tender externally funded highway improvement projects, report to Cabinet, 4 November 2026, and its appendices A to E (general arrangement drawings).
- Bury Council, Streets for All pages for Ramsbottom, Radcliffe and Bury town centre links, read on 1 November 2026.